Construct Biological Pharmenceutical Complex Building
 

 

Project Description : The Biological Sciences/Pharmaceutical Complex, was authorized by the 2005 General Assembly and will construct a 281,000 gross square foot facility that includes some "shell space" to allow for the growing research needs.This "shell space" will be fitted out for research laboratories at a later date as university funds and/or grant dollars become available.This new building will provide the college with a state-of-the-art facility that will also allow the college to expand enrollment to address the shortage of pharmacists in Kentucky.The College of Pharmacy will relocate to this new facility and vacate their existing space. In addition to the current Pharmacy Building, college faculty members are housed in 10 buildings on and off campus.Consolidation of the research and teaching expertise of the eighth ranked College of Pharmacy in the U.S. will further strengthen the instruction of students and research collaboration among faculty.The project is expected to be complete by December 2009.

 

 

UK Project Manager: Rich Riedl riedl@email.uky.edu
Consultants: EOP Architects
Contractor: Messer Construction (Construction Manager)
Construction Start: 01/08

Project Status: Exterior sitework, exterior coping/sun shade installation on south and east elevations and Commissioning continues.MEP work continues on basement, first and second floors.Second floor final finishes continue.First floor drywall hanging and finishing continues.Vivarium ceiling fixture installation and painting of the epoxy walls, ceilings and floors in the vivarium continues.Training begins in November with final inspections occuring throughout the month.

University of Kentucky
Capital Project Management Division
Room 222 Peterson Service Building
Lexington, KY 40506-0005
(859) 257-5911 Fax (859) 323-1017

Last update: 11/17/09

An Equal Opportunity University | email to: cpmdpagemaster

Project is on schedule to complete December 1, 2009 for vivarium (basement) first, second, and third floors.

Location: 789 South Limestone (Click here for link)
Square Feet: 277,800 GSF
Project Scope: $132,792,000
Source of Funds: State Bond Funds
Completion: 02/10

Major Features:

  • Glass Atrium
  • Commons Area
  • Two large lecture halls
  • Vivarium
  • Teaching Labratories
  • Faculty offices