Project Description: This project will entail replacing existing batteries and air conditioning units in the existing computing facility in McVey Hall to ensure sufficient power distribution and cooling for the next few years.UKIT will continue development of long term plans for a new facility. |
|
| UK Project Manager: Sandy Redmon sredmon@email.uky.edu | |
| Consultants: CMTA | |
| Contractor:TP Mechanical | |
| Construction Start: 11/09 | |
Project Status: A purchase order for the chiller has been issued.The bids were opened on October 6th.TP Mechanical was the low bidder.The bid was awarded and substantial completion is scheduled for mid-March, 2010. |
|
| Location: McVey Hall, Main Campus | |
| Project Scope: | |
| Source of Funds: | |
| Completion: 03/10 | |
| Major Features: | |
| New cooling units for computer room. | |