| Project Description: This project will entail replacing existing batteries and air conditioning units in the existing computing facility in McVey Hall to ensure sufficient power distribution and cooling for the next few years.UKIT will continue development of long term plans for a new facility. |
|
| UK Project Manager: Sandy Redmon sredmon@email.uky.edu | |
| Consultants: CMTA | |
| Contractor:TP Mechanical | |
| Construction Start: 11/09 | |
Project Status: Substantially complete. |
|
| Location: McVey Hall, Main Campus | |
| Project Scope: | |
| Source of Funds: | |
| Completion: 03/10 | |
| Major Features: | |
| New cooling units for computer room. | |

University of Kentucky
Capital Project Management Division
Room 222 Peterson Service Building
Lexington, KY 40506-0005
(859) 257-5911 Fax (859) 323-1017
Last update: 08/04/10