Project Description: This project provides a new surgical suite to be constructed in the shell space of the new Patient Care Facility.The project includes construction of 8 operating rooms, 1 hybrid OR, with supporting spaces for surgical pathology, surgical pharmacy, anesthesiology, staff lounge and lockers, and pre-operative/post operative functions.Also included will be the construction of a new central sterile supply and associated elevators to serve the new surgery areas.In addition the project will supply a 63,000 CFM air handling unit to provide for the HVAC requirements of this area.The fit-up encompases an area of aproximately 66,000 SF.
|
|
| UK Project Manager: Raymond Haunsz raymond.haunsz@uky.edu | |
| Consultants: GBBN | |
| Contractor:Turner Construction Co. | |
| Construction Start:12/06/10 | |
Project Status: Bids for this project were received on November 11, 2010.Turner has completed post bid interviews, and all subcontractors are under contract.All contractors are working to complete submittals and shop drawings.Wall layout is complete.Metal stud framing and Mechanical and electrical rough in work is in progress.Minor demolition is complete.Coordination meetings with major equipment vendors are taking place.The expected project completion date is November 2011. |
|
| Location: UK Hospital | |
| Square Feet: . 66,000 | |
| Project Scope: 35,000,000 | |
| Source of Funds: UK Hospital | |
| Completion: 11/29/11 | |

University of Kentucky
Capital Project Management Division
Room 222 Peterson Service Building
Lexington, KY 40506-0005
(859) 257-5911 Fax (859) 323-1017
Last update: 4/29/11