Project Description: This project provides for emergency repairs to the pedestrian bridge which crosses Cooper Drive.The bridge has numerous corrosion issues, electrical problems, and settling issues. BFMJ Structural Enginners has been contracted to evaluate the current condition of the bridge and design repairs and upgrades which will extend the service life for the forseeable future.The bridge supports student pedestrian traffic which crosses Cooper Drive midway between S. Limestone and University Drive.It is integral to connecting the campusses of the college of Agriculture.
|
| UK Project Manager: Raymond Haunsz raymond.haunsz@uky.edu |
| Consultants: BFMJ |
| Contractor: Structural Systems Repair Group |
| Construction Start: 4/07/2011 |
Project Status: Project plans have been completed and submitted for distribution.A project pre-bid meeting was held on March 9,2011. Project bids were received March 29, 2011and the project remains in budget.The expected completion date is October 2011. |
| Location: Cooper Drive |
| Square Feet: . |
| Project Scope: $1,055,700 |
| Source of Funds: |
| Completion: 10/25/2011 |