University of Kentucky
Capital Project Management Division
Room 222 Peterson Service Building
Lexington, KY 40506-0005
(859) 257-5911 Fax (859) 323-1017
Last update: 4/25/11
Project Description The University is the recipient of a grant award from the National Institute of Standards and Technology (NIST) as part of the "America Recovery and Renewal Act" federal stimulus package to construct a new stand-alone laboratory building for the University of Kentucky Center for Applied Energy Research located at Spindletop Research Park. Portions of the laboratory facility will be specially equipped to accommodate battery-manufacturing R&D. In addition, other portions of the building will be specially equipped to accommodate research related to biomass energy and biofuels, electrochemical energy storage, and solar energy.
|
|
| Location: Research Park Drive, Lexington KY (click for link) | |
UK Project Manager: Keith Ingram |
|
| Consultants: Murphy + Graves Architects | |
| Contractor: | |
| Construction Start: September 2010 | |
Project Status: Work completed in March, included completion of drilling of the geothermal wells, with the installation of the branch feeders ongoing from the wells to the vault. Structural steel is complete, with detailing continuing in all areas. Underground sanitary continues with acid waste pit being installed in early April. Column base plates are being grouted and box outs are ongoing. Storm line rerouting is complete. Exterior concrete masonry walls are being installed in Area “A”, along the elevator pit. Work in April will continue the installation of the CMU walls. Detailing on the steel to continue through April. Connections between the geothermal wells and the feeders will continue. Underground sanitary and acid waste pit to continue. Begin the underground electric rough-in. The slab on deck is scheduled to be poured. Exterior metal stud wall framing and sheathing is anticipated to begin. Bids were received on Bid Package #3, including the remaing Trade Contracts, on March 10th. This package included seventeen (17) trade contracts, including all interior finishes, including laboratory casework and controlled environment rooms, exterior finishes, sitework and MEP. Seven (7) of the trade contracts will be awarded, with seven (7) trade contracts to be re-bid incorporating the approved “value engineered” options and one to be awarded after a post bid addendum is issued. The remaining (2) trade contracts were rejected and will be deferred or eliminated from the scope of the project. The consultant and construction manager teams will prepare revisions for the re-bid packages to advertise after mid-April. |
|
| Major Additions: | |
| Project Scope: 3,500,000 | |
| Completation: 10/27/11 | |
