Contracts
Answer Outline
Fall '94
Question 1 -- 25 pts.
- Misunderstanding
- Effect of Peerless (Consensus Ad Idem)
- Restatement Analysis
- Materiality
- Reason to know 7 pts.
- Remedy (Homeowners)
- Expectancy Cost Completion
- + Down payment
- - Contract Price
- 17K+5K-20K = 2K -- 3 pts.
- Replacing of Wallpaper 5K 3 pts.
- (Cost completion or diminution in value)
- Rent of Hall ($500)
- Remedy (Carl)
- Expectancy
- Contract Price
- - Market Price
- Down Payment
- - Expenses
...............................3 pts.
- 20K-15K = 5K
- - 5K-3K = 2K
- ...................3K
- Reliance
- 7500
- -2000
- 4500
- (Capped by Expectancy) 3 pts.
- Mitigation 3 pts.
Question 2 -- 50 pts.
- Initial Contract
- Offer/Acceptance 5 pts.
- "We offer"
- Distribution of Offer
- No way to limit the number who could accept
- Mike acceptance?
- New Offer?
- Acceptance by Theresa?
- Output/Requirement K/Certainty 8 pts.
- Output contract -- generally
- Illusory promise
- Req. K? (is this intended to be a
combination output/requirement contract?)
- Certainty
- will take output for a while
- Basis for granting a remedy?
- Reliance on Relationship 5 pts.
- Theresa turned away offer mfr.
- Reasonableness of Reliance (K lacked duration)
- Breach by Plastics 10 pts.
- Output K
- Stated Estimate
- discontinuing output
- good faith issues
- characterization of output -
- dinosaurs vs. plastic toys
- Settlement -- 2d telephone Call
- O/A issue 5 pts.
- Plastics "would consider"
- Consideration 5 pts
- Duncan v. Black
- Did Toy have a valid K?
- 3d Call 5 pts.
- Offer $10,000
- Rejection
- Attempted Acceptance
- Remedy 7 pts
- Mp - Kp $25,000
- How many?
- Settlement 10K
- Is Theresa limited by final
"contract = problem pre-existing
dirty rule. No consideration for her
promise to take 10K
Question 3-- 8 pts.
- "On Completion of Work"
- Unilateral v. Bilateral
- bias toward bilateral
- If unilateral no damages
- option to complete but no promise
- If bilateral, damages = $1,000
Question 4-- 8 pts.
- Conditional Promise problem
- If Sara decides to buy (mutuality?)
- Acceptance by Sara
Question 5 -- 8 pts.
- Pre-existing Duty
- Cancellation of 1st K