PART I.
Multiple Choice
1. For the level aggregate plan, fluctuations in
demand are absorbed by
a. Inventory
and subcontracting.
b. Back orders and
price changes.
c. Inventory
and back orders.
d. Price
changes and subcontracting.
e. Subcontracting
and back orders.
2. After an aggregate plan is developed, it should
be evaluated in terms of all of the following except
a. Cost.
b. Revenue.
c. Operations.
d. Human
resources.
e. Customer
service.
3. In the basic
EOQ model, if the cost of placing an order doubles, and all other values remain
constant, the EOQ will
a. increase by
about 41%.
b. increase by
100%.
c. increase by
200%.
d. increase, but
more data is needed to say by how much.
e. either
increase or decrease.
4. Which of the
following statements about the basic EOQ model is true?
a. If the
ordering cost were to double, the EOQ would rise.
b. If annual
demand were to double, the EOQ would increase.
c. If the
carrying cost were to increase, the EOQ would fall.
d. If annual
demand were to double, the number of orders per year would increase.
e. All of the
above.
5. Which of the
following statements regarding the production order quantity model is true?
a. It applies
only to items produced in the firm's own production departments.
b. It relaxes
the assumption that all the order quantity is received at one time.
c. It relaxes
the assumption that the demand rate is constant.
d. It minimizes
the total production costs.
e. It minimizes
inventory.
6. Activity D
has predecessors B and C, and has successor F. D has duration 6. B's earliest
finish is 18, while C's is 20. F's late start is 26. Which of the following is
true?
a. B is a
critical activity.
b. C is
completed before B.
c. D has no
slack but is not critical.
d. D is
critical, and has zero slack.
e. None of the
above.
7. The critical
path for the network activities shown below is _____ with duration ______.
Activity |
Duration |
Immediate Predecessors |
A |
10 |
--- |
B |
8 |
--- |
C |
2 |
A |
D |
4 |
A |
E |
5 |
B,C,D |
a. A-C; 12
b. A-D-E; 19
c. B-E; 13
d. A-B-C-D-E;
29
e. none of the
above
8. Suppose activity
D can be shortened from 4 weeks to 1 week. Assume all other activity times
remain the same. How much shorter will the total project earliest completion
time become?
a. 0 weeks
b. 1 week
c. 2 weeks
d. 3 weeks
e. 4 weeks
9. A PERT project
has 45 activities, 19 on the critical path. The estimated time for the critical
path is 120 days. The sum of all activity variances is 64, while the sum of
variances along the critical path is 36. The probability that the project can
be completed between days 108 and 120 is
a. -2.00
b. 0.0227
c. 0.1058
d. 0.4773
e. 0.9773
10. Two
activities are candidates for crashing. Activity details are in the table
below. To cut one day from the project's duration, activity _____ should be
crashed first, adding ______ to project cost.
Activity |
Normal Time |
Normal Cost |
Crash Time |
Crash Cost |
One |
8 days |
$6,000 |
6 days |
$6,800 |
Two |
10 days |
$4,000 |
9 days |
$5,000 |
a. One; $400
b. One; $6,800
c. Two; $1,000
d. Two; $5,000
e. One or two should
be crashed; $1,400
PART II. Problem Solving
Question 1.
C&A has the following aggregate demand
requirements and other data for the upcoming four quarters.
Quarter |
Demand |
|
Previous quarter's output |
1500 units |
1 |
1300 |
|
Beginning inventory |
200 units |
2 |
1400 |
|
Stockout cost |
$50 per unit |
3 |
1500 |
|
Inventory holding cost |
$10 per unit at end of
quarter |
4 |
1300 |
|
Hiring workers |
$4 per unit |
|
|
|
Firing workers |
$8 per unit |
|
|
|
Unit cost |
$30 per unit |
|
|
|
Overtime |
$10 extra per unit |
Which of
the following production plans is better:
Plan A—chase demand by hiring
and firing; or
Plan B—produce at a constant
rate of 1200 and obtain the remainder from overtime?
Question 2.
The
C&A Company stocks, among many other products, a certain container, each of
which occupies four square feet of warehouse space. The warehouse space
currently available for storing this product is limited to 600 square feet.
Demand for the product is 15,000 units per year. Holding costs per year are 4%
of item cost which is $100. Ordering
costs are $5 per order.
a. What is the
cost-minimizing order quantity (i.e., EOQ) decision for C&A?
b. What is the
total inventory-related cost of this decision?
c. What is the
total inventory-related cost of managing the inventory of this product, when
the limited amount of warehouse space is taken into account?
d. What would
the firm be willing to pay for additional warehouse space?
e. What is the
reorder point if lead time is 7 days (assume 300 working days a year)?
f. Show
graphically how the inventory level fluctuates against time under the EOQ
model.
g. Show
graphically how the total inventory cost changes against order quantity.
h. C&A
Company decides to produce the container instead at a production rate of 20,000
units per year. Set-up costs are $10 per
production run. Holding costs per year
are 4% of item cost which is $80. What
is the economic production quantity?
i. Show
graphically how the inventory level fluctuates against time under the situation
described in (g)?
j. C&A
Company pays a supplier $100 per container but $80 per
container if they manufacture the containers themselves. Given the item cost information, should
C&A produce or purchase the containers?
k. The supplier
offers C&A a discount of 5% if the order quantity exceeds 200. Should C&A take advantage of the
discount?
Question 3.
Consider the tasks, durations, and predecessor
relationships in the following network.
Activity Description |
Immediate Predecessor(s) |
Optimistic (Weeks) |
Most Likely (Weeks) |
Pessimistic (Weeks) |
A |
--- |
4 |
7 |
10 |
B |
A |
2 |
8 |
20 |
C |
A |
8 |
12 |
16 |
D |
B |
1 |
2 |
3 |
E |
D, C |
6 |
8 |
22 |
F |
C |
2 |
3 |
4 |
G |
F |
2 |
2 |
2 |
H |
F |
6 |
8 |
10 |
I |
E, G, H |
4 |
8 |
12 |
J |
I |
1 |
2 |
3 |
a. Develop a network diagram for this project
using AON notation.
b. Based on the
calculation of estimated times, what is the critical path?
c. What is the estimated
time of the critical path?
d. What is the
activity variance along the critical path?
e. What is the
probability of completion of the project before week 42?
f. If C&A
wants a 95% probability of being done on time, what is the expected project completion
time?